Comprehensive Plan
In order to assess the current situation of the network, find its weaknesses and plan to develop the network in coming years a comprehensive plan is needed.
As required by Iran Power Generation and Transmission Company (TAVANIR), the steps needed to conduct a comprehensive study of a network are:
- Gathering and preparing information, such as clients' billings, GIS, master plan maps, feeder and substation information, blackout information, switching information, distribution substation loading, etc.
- Load estimation: estimation of current load density and that of the following years.
- Performing load flow studies, reliability studies and short circuit studies.
- Designing the electrical network for the target year considering the limitations imposed by the employer.
- Designing the interim electrical network, defining the gradual steps to reach the target network.
- Presenting reports.
BCE is ready to perform such studies with efficiency, accuracy and speed. We've developed softwares that can optimize the location of distribution and sub-transmission substations, power switches and protection gears. You can check out the list of these softwares here.